NAME OF PROJECT     KERN RIVER GAS TRANSMISSION

            COMPANY

                                                                                     SPREAD 6

 

Location                                                                        St. George, Utah

 

Owner                                                                           Kern River Gas Transmission Company

Point of Contact                                                             Mike Dunn

                                                                                     (801) 584-6762

Inspection Agency                                                          The Williams Companies

Date Contract Awarded                                                   July, 2002

Basis of Award                                                               Competitive Bid

Date Work Started                                                          August, 2003

Scheduled Completion Date                                            March, 2003

Actual Completion Date                                                  March, 2003

Contract Duration                                                           7 Months

Pipe Length (Miles)                                                         63.8 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       36-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct 59.7 miles of 36-inch heavy-wall

                                                                                     Pipeline


 

NAME OF PROJECT                                         KERN RIVER GAS TRANSMISSION

COMPANY        SPREAD 7

 

Location                                                                        Washington County, Utah; Clark & Lincoln

                                                                                     Counties, Nevada

 

Owner                                                                           Kern River Gas Transmission Company

Point of Contact                                                             Mike Dunn

                                                                                     (801) 584-6762

Inspection Agency                                                          The Williams Companies

Date Contract Awarded                                                   July, 2002

Basis of Award                                                               Competitive Bid

Date Work Started                                                          December, 2002

Scheduled Completion Date                                            March, 2003

Actual Completion Date                                                  March, 2003

Contract Duration                                                           4 Months

Pipe Length (Miles)                                                         85 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       36-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct 88.9 miles of 36-inch heavy-wall

                                                                                     Pipeline utilizing a mechanized welding method.


 

 

NAME OF PROJECT                                         KERN RIVER GAS TRANSMISSION

                                                                                    COMPANY

                                                                                     SPREAD 8

 

Location                                                                        Clark County, Nevada; San Bernardino County,

                                                                                     California

 

Owner                                                                           Kern River Gas Transmission Company

Point of Contact                                                             Mike Dunn

                                                                                     (801) 584-6762

Inspection Agency                                                          The Williams Companies

Date Contract Awarded                                                   July, 2002

Basis of Award                                                               Competitive Bid

Date Work Started                                                          December, 2002

Scheduled Completion Date                                            March, 2003

Actual Completion Date                                                  March, 2003

Contract Duration                                                           4 Months

Pipe Length (Miles)                                                         54.4 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       36-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct 54.4 miles of 36-inch heavy-wall

                                                                                     Pipeline


 

NAME OF PROJECT                                         WILLIAMS GAS PIPELINE – WEST

 

 

Location                                                                        Thurston & Grays Harbor Counties,

                                                                                     Washington

 

Owner                                                                           The Williams Companies

Point of Contact                                                             Ken Steele

                                                                                     (801) 584-6924

Inspection Agency                                                          The Williams Companies

Date Contract Awarded                                                   November, 2001

Basis of Award                                                               Competitive Bid

Date Work Started                                                          June, 2002

Scheduled Completion Date                                            December, 2002

Actual Completion Date                                                  December, 2002

Contract Duration                                                           6 Months

Pipe Length (Miles)                                                         49 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       20-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct 49 miles of 20-inch heavy-wall

                                                                                     Pipeline and six horizontal directional drills


 

NAME OF PROJECT                                         ALLIANCE PIPELINE L.P. –

                                                                                     SPREAD 3

 

Location                                                                        Richland County, North Dakota to

                                                                                     Mankato, Minnesota

 

Owner                                                                           Alliance Pipeline, L.P.

Point of Contact                                                             L.A. “Buster” Gray

                                                                                     (713) 977-7770

Inspection Agency                                                          Universal ENSCO, Inc.

Date Contract Awarded                                                   November, 1998

Basis of Award                                                               Competitive Bid

Date Work Started                                                          May, 1999

Scheduled Completion Date                                            July, 2000

Actual Completion Date                                                  July, 2000

Contract Duration                                                           2 Years

Pipe Length (Miles)                                                         160 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       36-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct 160 miles of 36-inch heavy-wall

                                                                                     pipeline (MAOP 1750 psig) utilizing a

                                                                                     mechanized welding method.  To be completed

                                                                                     over a two-year construction period.


 

NAME OF PROJECT                                         NORTHERN BORDER CHICAGO

                                                                                    PROJECT – SPREAD 2

 

Location                                                                        Ventura to Marshalltown, Iowa

Owner                                                                           Northern Border Pipeline (ENRON)

Point of Contact                                                             Paul Fuhrer, Project Director

                                                                                     (402) 398-7733

Inspection Agency                                                          Willbros Company - Tulsa, Oklahoma

Date Contract Awarded                                                   March, 1998

Basis of Award                                                               Competitive Bid

Date Work Started                                                          April, 1998

Scheduled Completion Date                                            November, 1998

Actual Completion Date                                                  November, 1998 On Schedule

Contract Duration                                                           Seven Months

Pipe Length (Miles)                                                         76.54 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       36-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct and make ready for service, including

                                                                                     cleaning, testing and drying Spread 2 of the

                                                                                     Chicago Project.


NAME OF PROJECT                                         TRANSCOLORADO GAS PIPELINE

                                                                                     PROJECT - SPREAD 3

 

Location                                                                        Olathe to near Delores, Colorado

Owner                                                                           TransColorado Gas Transmission Company

Point of Contact                                                             Steve Dracus, Project Director

                                                                                     (713) 977-7770

Inspection Agency                                                          Universal ENSCO, Inc.

Date Contract Awarded                                                   July, 1998

Basis of Award                                                               Competitive Bid

Date Work Started                                                          July, 1998

Scheduled Completion Date                                            December, 1998

Actual Completion Date                                                  December, 1998

Contract Duration                                                           Six Months

Pipe Length (Miles)                                                         80.1 Miles

Pipe Material                                                                  Steel

Pipe Size                                                                       22-Inch Diameter

Fluid Handling                                                                Natural Gas

Firm's Scope of Work                                                     Construct and make ready for service, Spread 3

                                                                                     within the permit parameters including

                                                                                     environmental and wildlife construction

                                                                                     windows.